For an 8x10 shed with a 1 ft border, a 4 in gravel pad takes about 1.6 cubic yards (roughly 2.3 tons with compaction), a 4 in concrete slab takes about 1.1 cubic yards (49 bags of 80 lb mix), and a 16 in paver base takes 48 pavers. Gravel is usually the cheapest and drains best under resin and metal kits.

Shed foundation calculatorUpdates as you type

Gravel pad: 2.3 tons, about $103

Gravel pad size
10 x 12 ft
Gravel (4 in, compacted)
1.63 yd³ / 2.3 tons
Concrete slab (4 in)
1.09 yd³ / 49 bags of 80 lb
Concrete material cost
$319
16 in pavers
48 pavers
Paver base (4 in gravel + 1 in sand)
1.5 t gravel + 0.3 t sand
Paver material cost
$275
Weed fabric for the pad
120 sq ft

Material costs only; add delivery and rental of a plate compactor.

Foundation kits and site prep tools

Matched to this result, spread from budget to premium.

Prices change often; the button shows today's price on Amazon.

Which shed foundation is best?

For resin and steel kits under about 150 sq ft, a compacted gravel pad inside a treated timber frame is the best value: it drains, stays level, and costs a fraction of a slab. Concrete is the right call for heavy use (a garage-sized shed, a workshop, a riding mower driven in daily) or when the kit's floor is thin and needs a rigid base. Pavers sit between the two: neat and flat, but slower to level than gravel. Gravel vs concrete covers the tradeoffs in detail.

The assumptions behind each number

InputDefaultBasis
Gravel border1 ft each sideCommon kit instruction; catches roof drip
Gravel density1.4 t per cubic yardSupplier conversion for 3/4 in crushed stone
Compaction allowance+10%Trade convention
80 lb concrete bag yield0.6 cu ftPrinted on the bag
Concrete waste+10%Trade convention
Paver base4 in gravel + 1 in sandStandard paver installation

Prices are defaults you can change. Quarries typically deliver a minimum of several tons, so small pads may cost the delivery minimum rather than the per-ton price.

More shed calculators

Frequently asked questions

Can I put a shed directly on the ground?

Not for long. Bare soil holds moisture against the floor, settles unevenly and lets the doors rack out of alignment. Even a small resin shed does better on a few inches of compacted gravel or a plastic grid foundation kit, which keeps the floor dry and level for far longer than grass or dirt.

How thick should a shed slab be?

Four inches of concrete over a compacted gravel sub-base is standard for storage sheds. Go to 6 in, or thicken the edges, if you will drive a lawn tractor in regularly or build a large workshop. The calculator shows both so you can see the extra bags.

Is a plastic shed foundation kit as good as gravel?

For small and mid-size resin sheds on reasonably level ground, grid kits work well: they lock together, spread the load and drain. On a slope, or for a large or heavy shed, a proper compacted gravel pad inside a timber frame is more forgiving.

This page is researched guidance, not professional engineering, legal or building-code advice. Sizes, loads and permit rules vary by product and by town: check your local code and the kit manufacturer's instructions before you build.